Start with the right request

One question decides the path: is the work in state-funded space and covered by FM, or is it rechargeable to your department? Answer that first and your request goes to the right shop without a round of follow-up.

See which path applies

Contact FM before submitting

Two request paths, decided by funding

FM covers routine maintenance and repair of state-funded space at no cost to your department. Everything else is rechargeable and goes through a Facilities Service Request.

The routing question

Is the space state-funded, and is the work routine maintenance or repair of building systems? If yes, submit a Service Request. If the space is non-state funded, or the work is an alteration, addition, upgrade, removal, or anything on department-purchased equipment, submit a Facilities Service Request. If you are not sure which applies, contact FM before you submit.

Service Request

Routine maintenance and repair of state-funded buildings, building systems, grounds, and public areas. No charge to your department.

  • Temperature or HVAC issue
  • Leaking faucet, clogged drain, roof leak
  • Relamping and routine building repair
  • Preventive maintenance on building-integrated, state-purchased equipment

FSR

Rechargeable work: alterations, additions, upgrades, removals, non-state-funded space, and department-owned equipment. Billed to your FAU.

  • Office or lab refresh, paint, flooring, signage
  • Equipment or workstation additions and relocations
  • Keys, re-keying, and lock changes
  • Special event setup and event custodial support

Every FSR is one of two types

Blanket and Estimate are not separate front doors. You choose between them inside the Facilities Service Request.

FSR Type 1

Blanket Work Order

For low-dollar-volume, routine work that does not need an estimate. Your blanket number is your standing FM account, linked to your FAU, and stays open until you cancel it.

  • Keys and signage
  • Furniture moving and bulletin boards
  • Small recurring recharge work

Estimate Required: No

Lead Time: Minimum 5 working days

Billing: Monthly, as charged

FSR Type 2

Estimate / Non-Blanket Work Order

For work that needs scope development, scheduling, coordination, or cost approval. FM estimates the work in writing and you approve or reject it before anything starts.

  • Complex or multi-craft scope
  • Alterations with infrastructure impact
  • Anything you need a written cost for

Estimate Required: Yes, in writing

Typical Completion: 30 to 60 calendar days

Billing: 75% on approval, 25% at completion

What happens after you submit

The same four steps apply to both paths. Where they differ is the estimate and the bill.

Step 1 - Intake

FM Customer Service receives the request, assigns a work order number, and screens the approval.

Step 2 - Contact

For an FSR, the FM Project Manager contacts you within five working days to confirm scope.

Step 3 - Estimate and approval

Non-blanket work is estimated in writing. Work starts only after you approve it.

Step 4 - Execution and closeout

The assigned shop performs the work. FM marks the job complete and Accounting bills monthly.

How fast, and by when

Every request is classified into one of six priority levels. The level sets the response commitment, not the submission date.

PriorityWhat it coversResponseResolution
EmergencyImminent threat to life, property, security, or environmentImmediateMitigate within 24 hours
UrgentPotential threat: broken glass, all lights out, roof leak, elevator repairWithin 24 hoursMitigate within 72 hours
RoutineNo immediate risk: painting, cracked glass, broken furniture, key requestContact within 3 working daysComplete within 15 working days
CalendaredDate-specific work: events, setups, moves, scheduled inspectionsScheduledBy the agreed due date
ProjectMulti-craft or complex work: renovations, capital replacementsPer project schedulePer project schedule
Preventative MaintenanceScheduled servicing of building integrated equipmentPer PM schedulePer manufacturer specification

What it costs and when you are billed

Applies to Facilities Service Requests only. Service Requests in state-funded space carry no charge to the department.

Written estimates only

FM does not issue verbal estimates. A written estimate is what makes the billing accurate and is what you approve against.
 

75 / 25 billing

On an estimated job, 75 percent is charged when you approve the estimate and the remaining 25 percent when FM marks the job complete.

Track it yourself

Billing on the Web shows work orders, descriptions, liens on pending estimates, time and materials detail, and archived bills by department and FAU.

Have this ready before you submit

Complete information is the difference between a request that routes on the first pass and one that comes back to you for detail.
 

Every request

  • Building name, floor, room number, and exact location
  • Description of the issue, the request, or the outcome you need
  • Whether the work is a repair, addition, upgrade, removal, relocation, or change in use of space
  • Preferred timing, access limitations, shutdown needs, and operational constraints
  • Whether utilities, HVAC, power, plumbing, data or network, safety, or building systems may be affected
  • Whether the space is a lab, clinical, research, server or network, or otherwise specialized

Required for an FSR

  • Your four-digit department code
  • The Full Accounting Unit (FAU) to be charged
  • The approver's name and email, plus any copy recipients
  • Your blanket number, if the work is going against an existing blanket
  • Whether the request relates to another open request or project
  • For key orders: delivery or pickup, delivery address, and the person authorized to receive
Why this is required: The recharge path collects funding and an authorizer up front. Without them the request cannot be posted and Customer Relations has to call you back before anything moves.

When your request goes beyond FM

Some work triggers review by Design & Project Management or a campus partner before it can be scheduled. Knowing this in advance prevents a restart.

Dollar thresholds

Minor renovations and alterationsUp to $100,000
Referred to Design & Project ManagementOver $100,000
Managed by DPMUp to $3M
Above $3MChancellor delegation

Change in use of space

Converting an office to a lab, changing a room's function, adding specialized equipment, or altering infrastructure changes the space record and the fund type that governs it. Contact FM before the request is submitted so the space review happens first, not after the work is scoped.

EH&S

Safety, environmental, occupational health, and regulatory review. Renovation, alteration, repair, and construction maintenance may carry Cal/OSHA requirements depending on scope.

Design & Project Management

Larger or more complex work needing design, project coordination, or specialized project support.

Capital Programs

Projects over $100,000, or requests that change the use of space.

Procurement, IT, partners