Overview of Energy Conservation Measures in the Building:

•  Replaced and/or upgraded aging and inefficient HVAC equipment and controls
•  Installed occupancy sensors for HVAC and future lighting control
•  Reinforced the campus standard for temperature setpoints
•  Programmed mechanical system to operate based on building schedules
•  Added capability to control building systems down to the room level

Fact Sheet - General Areas

Overview of Energy Conservation Measures in the Ceramic & Sculpture Studios:

•  Converted system to variable air volume control for ventilation demand capability
•  HVAC lockout sensors installed on overhead and side doors
•  Purge button added to switch system to maximum ventilation mode for 1 hour

Fact Sheet - Ceramic & Sculpture Studios

Overview of Energy Conservation Measures:

•  Optimized mechanical system sequences of operation
•  Installed occupancy sensors for lighting in some areas
•  Optimized air handling unit schedules

Future Planned Work in the Building:

•  LED lamp/fixture replacement
•  Additional occupancy sensors to control ventilation and lighting systems
•  Upgrade building system controls down to the room level
•  Provide ventilation based on space use and operational needs
•  Reinforcement of the campus standard for temperature setpoints

Overview of energy conserving measures for the building:

•  Installed occupancy sensors for ventilation and lighting controls
•  Reinforced the campus standard for temperature setpoints
•  Programmed mechanical system to operate based on building schedules
•  Late start system ramp up to reduce steam demand from the Cogen plant

Fact Sheet

Work in Progress Buildings and Labs

Phase 2-3: Duct Cleaning/Pre-Construction

Overview of Duct Cleaning:


•  All supply air duct work will be cleaned except in the vivarium
•  Interior supply air duct lining will be encapsulated
•  Supply diffusers and exhaust grilles will be cleaned
•  All supply air post-filters and obstructions will be removed

Duct Cleaning Impacts to Building Occupants:

•  Duct cleaning will start at night and stopped in the early morning
•  Supply air will be shut off on a nightly basis (vivarium will remain on)
•  Temperature sensitive spaces, equipment may be affected
•  Animals, flies will not have temperature control while air is off
•  Unsafe to work while supply air is turned off

Duct Cleaning Schedule
Town Hall Meeting - Slide Presentation
Fact Sheet


Overview of Construction:

•  Vivarium is excluded from the scope of work
•  Upgrade existing air valves
•  Install system controls and programming

Overview of Energy Conservation Measures:

•  Provide ventilation based on space use and operational needs
•  Add capability to control building systems down to the room level
•  Optimize mechanical system sequences of operation
•  Reinforcement of the campus standard for temperature setpoints
•  Re-balance air for the entire building

Phase 2-3: Pre-Construction

Overview of Construction:

•  Vivarium is excluded from the scope of work
•  Upgrade existing air valves
•  Install system controls and programming

Overview of Energy Conservation Measures:

•  Provide ventilation based on space use and operational needs
•  Add capability to control building systems down to the room level
•  Optimize mechanical system sequences of operation
•  Reinforcement of the campus standard for temperature setpoints
•  Re-balance air for the entire building

Phase 2: Design

Overview of Energy Conservation Measures:


•  Provide ventilation based on space use and operational needs
•  Optimize mechanical system sequences of operation
•  Reinforcement of the campus standard for temperature setpoints
•  Re-balance air for the entire building
•  Optimize glass washer exhaust controls
•  Increase exhaust stack height to improve building exhaust discharge